» HOME

  » ABOUT US

  » RULES

  » FEES

  » MEMBERSHIP

  » NEWS & EVENTS

  » ARTICLES

  » CONTACT US

Articles

This section features articles and write-ups contributed by members of PDRCI. The opinions and views expressed by the contributors are not necessarily the opinions of PDRCI, its Officers and staff.


Philippine ArbitrationUpdates:


Fort Bonifacion Development Corporation v. Domingo,
G.R. No. 180765, February 27, 2009; 580 SCRA 397;
 
Fort Bonifacio Development Corporation v. Sorongon & Fong,
G.R. No. 176709, May 8, 2009, 587 SCRA 613
 
Abstract:
 
"The receivables of a contractor from the project owner arising from work on a construction project were assigned to a third person with notice to the project owner. When the project owner refused to pay the assignee because the assigned receivables were used to pay other creditors of the assignor which creditors obtained writs of garnishment on such receivables, it was held in Fort Bonifacio Development Corporation v. Nicolas Domingo, that the Regional Trial Court, not the Construction Industry Arbitration Commission [“CIAC”], had jurisdiction over the complaint for payment of a sum of money filed by the assignee against the project owner."

Read more...



HUTAMA-RSEA JOINT OPERATIONS, INC. v.
CITRA METRO MANILA TOLLWAYS CORPORATION
G.R. No. 180640, April 24, 2009 (3rd Div., Chico-Nazario, J.)


Both parties are domestic corporations.  The Respondent, Citra Metro Manila Tollways  Corporation  [“Citra”] is the general contractor and operator of the South Metro Manila Skyway Project [the “Project”] The Petitioner, Hutama-RSEA Joint Operations, Inc. [“Hutama”] was its subcontractor.  Citra and Hutama are referred to herein collectively as the “Parties”.  On September 25, 1996, the Parties entered into an Engineering Procurement Construction Contract [the “Contract”] whereby Hutama would undertake the construction of Stage 1 of the Project which stretched from the junction of Buenjdia Avenue, Makati City, up to Bicutan Interchange, Taguig City for a contract price of US$369,510,304.00.

Read more...



Equitable PCI Banking Corporation, et al v. RCBC Capital Corporation,

G.R. No. 182248, December 18, 2008; [Velasco, Jr., J.]


The parties executed a Share Purchase Agreement “SPA”] ] whereby  Equitable PCI Banking Corporation [“Equitable”] and the individual stockholders of Bankard, Inc,. [“Bankard”]  as sellers  [the “Sellers”]  sold to the RCBC Capital Corporation [“RCBC”]  the Sellers’ interests in Bankard representing 226,460,000 shares [the “Sold Shares”] for P1,786, 769,400. To expedite the purchase, RCBC agreed to dispense with the conduct of a due diligence audit on the financial status of Bankard.  The Sellers, however, made representations and warranties concerning the financial condition of Bankard and the SPA provided for remedies of RCBC for breach of those warranties.  The stipulated down payment was made after which RCBC was given full management and operational control of Bankard.  Sometime thereafter, the parties amended the SPA to include, among others, a provision that the remedy for a breach of the Sellers’ representation and warranty under Section 5 (h) of the SPA shall be available if the demand therefore is presented to the Sellers in writing, supported by appropriate substantiation,  on or before December 31, 2000. By September 2000, the RCBC audit team which was created for the purpose of auditing Bankard’s accounts had concluded that the warranty under Section 5 (h) was correct. On December 28, 2000, RCBC paid the balance of the contract price.

Read more...



Luzon Hydro Corporation v. Hon. Rommel O. Baybay, etc
and Transfield Philippines, Inc.,
CA-G.R. Sp. No. 94318, November 29, 2005



1.         The Validity of the Principle “Costs Follow The Event”

Under Philippine Law.

An arbitral tribunal in an ICC arbitration held in Singapore made a final award granting, modifying or rejecting some of the claims and counterclaims of the parties with the result that a net award of some US$12 million was made in favor of Transfield Philippines, Inc..[“TPI”].  In its Final Award, and on the issue of costs, the tribunal applied the principle of costs follow the event and directed Luzon Hydro Corporation [“LHC”] to pay TPI direct costs of the arbitration because “TPI had to commence this arbitration in order to achieve the net flow of funds in its favour”. The tribunal added that “had the counterclaim ever topped the claim the Tribunal would have taken a different view.  As to legal and other costs, the tribunal said that “it would be fair and reasonable in all the circumstances of this case to award to TPI a percentage of its legal and other costs….In the opinion of the Tribunal the appropriate percentage to take is 80%.”


Read more...



Empire East Land Holdings, Inc.
v. Capitol Industrial Construction
Groups, Inc., G.R. No. 168074,
September 26, 2008

 

During the construction period, changes in circumstances arose prompting the parties to make adjustments in the initial terms of their contract.  These included deletion of items of work and the consequent reduction of the contract  a change in the completion date of the contract. Empire East Land Holdings, Inc. [“Empire East”], the owner directed the contractor, Capitol Industrial Construction Groups, Inc. [“Capitol”]  to reduce the monthly target accomplishment to P1 million worth of work and up to one (1) floor only. In view of this, Capitol asked that the topping-off be moved to a later date.  It likewise requested a price adjustment with respect to overhead and equipment expenses and legislated labor cost.  These requests were not acted upon by Empire East.  After the completion of the side trimmings and excavation of the building’s foundation, Capitol demanded the payment of P2,248,507.70 and P1,805,225.90, respectively.  Instead of paying the amount, Capitol agreed with Empire East to reduce the claim for side trimming to P900,000.00.  Capitol’s claim for foundation excavation was not acted upon.  During the construction period, Empire East granted, on separate occasions, Capitol’s request for payroll and material accommodations.

Read more...



ABS-CBN Broadcasting Corporation v.
World Interactive Network Systems [WINS]
Japan Co., Ltd., G.R. No. 169332,
February 11, 2008


THE FACTS:

In 1999, ABS-CBN Broadcasting Corporation [“ABS-CBN”] granted World Interactive Network Systems Japan Co., Ltd. [“WINS”],  an exclusive license to distribute and sublicense the distribution of a television service known as “The Filipino Channel” [“TFC”] in Japan [the Licensing Agreement”]. In 2002, ABS-CBN, alleging breach, notified WINS of its intention to terminate the Licensing Agreement. WINS commenced arbitration pursuant to the arbitration clause in the Licensing Agreement alleging that ABS-CBN wanted to renegotiate the terms thereof to allow it to demand higher fees. The sole arbitrator thereafter appointed, after hearing, found in favor of WINS and ordered ABS-CBN to pay damages.

Read more...



Equitable PCI Bank v. Judge Oscar Pimentel,
RCBC Capital Corporation, Sir Ian Barker
and Neil Kaplan,
CA-G.R. Sp. No. 93966, March 30, 2007:


THE FACTS:

A dispute between Equitable PCI Bank [EPCI] and RCBC Capital Corporation [RCBC] was submitted to arbitration under ICC Rules. The Philippines was the place of arbitration. Two of the three members of the Tribunal, Sir Ian Barker and Neil Kaplan, are foreigners and non-members of the Philippine Bar.  EPCI moved to disqualify Barker and Kaplan on the ground that they are engaged in the practice of law in the Philippines and are therefore ineligible to rule on the merits of the issues  raised in the arbitration. In a petition filed with the RTC of Makati,  Judge Pimentel held: that the arbitral tribunal which includes a former justice of the Supreme Court and two foreign lawyers are not considered to be engaged in the practice of law in the Philippines.

Read more...



Diesel Construction Co., Inc. v.
UPSI Property Holdings, Inc.
G.R. No. 154885; UPSI Property
Holdings, Inc. v. Diesel Construction Co.,
Inc. and FGU Insurance Corp.,
G.R. No. 154937, March 24, 2008


THE FACTS:

This is a construction arbitration case filed with the Construction Industry Arbitration Commission [“CIAC”], initiated by Diesel Construction Co., Inc. [“Diesel”] against UPSI Property Holdings, Inc. [“UPSI”] for payment of the balance of the contract price, damages and attorney’s fees. UPSI filed an answer with counterclaim. The principal defense of UPSI was that Diesel was guilty of delay for which it should be held liable for the payment of liquidated damages.  After hearing, the CIAC arbitral tribunal found that the delays were attributable to UPSI and awarded to Diesel the amount of P4,027,861.60 plus interest. UPSI appealed by petition for review under Rule 43 of the Rules of Court to the Court of Appeals. The appeals court  partially reversed the Tribunal and found Diesel guilty of inexcusable delay of 45 days for which it was held liable for liquidated damages in the amount of P1,309,500.00 which should be deducted from the unpaid balance of the contract price amounting to P2,441,482.64.

Read more...




The case of Korea Technologies Co., Ltd. v.
Hon. Alberto A. Lerma  and Pacific General
Steel Manufacturing Corporation,
G.R. No. 143581, Jan. 7, 2008.


THE FACTS:

Korea Technologies Co., Ltd. [Korea Tech], a Korean corporation, entered into a contract with Pacific General Steel Manufacturing Corporation [Pacific General], a domestic corporation, whereby Korea Tech undertook to ship and install in Pacific General’s site in Carmona, Cavite the machinery and facilities necessary for manufacturing LPG cylinders, and to initially operate the plant after it is installed. The plant, after completion of installation, could not be operated by Pacific General due to its financial difficulties affecting the supply of materials.  The last payments made by Pacific General to Korea Tech consisted of postdated checks which were dishonored upon presentment. According to Pacific General, it stopped payment because Korea Tech had delivered a hydraulic press which was different in kind and of lower quality than that agreed upon. Korea Tech also failed to deliver equipment parts already paid for by it. It threatened to cancel the contract with Korea Tech and dismantle the Carmona plant.  Korea Tech initiated arbitration before the Korea Commercial Arbitration Board [KCAB] in Seoul, Korea and, at the same time, commenced a civil action before the Regional Trial Court [the “trial court”] where it prayed that Pacific General be restrained from dismantling the plant and equipment.  Pacific General opposed the application and argued that the arbitration clause was null and void, being contrary to public policy as it ousts the local court of jurisdiction. It also alleged that Korea Tech was not entitled to the payment of the amount covered by the two checks, and that Korea Tech was liable for damages.

Read more...


Should local courts interfere with the NAIA3 mess?
by: Mario E. Valderrama 

The Government had already abrogated the NAIA 3 contract. The Supreme Court sustained the Government by ruling the contract void and the arbitration clause unenforceable, with a concurring opinion saying that PIATCO is entitled to reimbursement as a builder (see Agan, Jr. vs. PIATCO, 402 SCRA 612 [2003]).

That should be the end of the story.

Read more....


International Commercial Arbitration: Its Relevance in the Philippines
By: Eduardo R. Ceniza

Introduction

While it is true that parties and arbitrators prefer to operate in a sort of special chamber to avoid, as far as possible, national law or national court rules, the fact remains that international commercial arbitration cannot avoid the incidence and influence of national law. For one thing, arbitration cannot take place totally without reference to its venue and, necessarily, the national law of the venue. The lex arbitri will certainly have an influence, if not a direct bearing, upon the procedural and other administrative aspects of the arbitration. For another thing, arbitrators do not have power over individuals or institutions who do not submit themselves to the jurisdiction of the arbitral tribunal. Thus, to bind third parties, for instance, to interim measures of protection, resort to the national court for assistance becomes unavoidable. Therefore, while international commercial arbitration may operate quite independently of national law, the national law of the place of arbitration will always be somewhere in the background. Indeed, national law provides the contextual framework in which all international commercial arbitrations take place.

Read more...


Interim Measures: The Role of the Arbitral Tribunal and the Courts
by:  Eduardo R. Ceniza

A. Interim measures; nature in general

The availability of interim measures can be critical to the effectiveness of arbitration and to the continued viability of the transaction. Indeed, in some cases, an arbitration may be an exercise in futility if interim relief cannot be obtained rapidly, e.g., to secure assets or to enjoin certain conduct......

Read more....


Why Litigate?  Arbitrate!
by:  Custodio O. Parlde

I.  Justice Delayed is Justice Denied

The question is often asked whether there is not in fact a denial of justice when civil disputes are resolved by a trial court for five (5) years on the average. Trial court dockets are hopelessly clogged. There are more cases being filed than are being resolved.  In addition, more than 30% of the salas of trial judges are vacant. The salary of a trial judge is not attractive enough to most lawyers. And yet as we grow in population and our economy improves the number of commercial transactions will correspondingly increase.  An important obstruction to the growth of business is the manner and speed by which commercial disputes are resolved.

Read more....



© 2005 by Philippine Dispute Resolution Center, Inc. (PDRCI)
Please contact us  for further information.



Steve's web templates