Empire East Land Holdings, Inc.
v. Capitol Industrial Construction
Groups, Inc., G.R. No. 168074,
September 26, 2008
During
the construction period, changes in circumstances arose prompting the
parties to make adjustments in the initial terms of their
contract. These included deletion of items of work and the
consequent reduction of the contract a change in the completion
date of the contract. Empire East Land Holdings, Inc. [“Empire
East”], the owner directed the contractor, Capitol Industrial
Construction Groups, Inc. [“Capitol”] to reduce the
monthly target accomplishment to P1 million worth of work and up to one
(1) floor only. In view of this, Capitol asked that the topping-off be
moved to a later date. It likewise requested a price adjustment
with respect to overhead and equipment expenses and legislated labor
cost. These requests were not acted upon by Empire East.
After the completion of the side trimmings and excavation of the
building’s foundation, Capitol demanded the payment of
P2,248,507.70 and P1,805,225.90, respectively. Instead of paying
the amount, Capitol agreed with Empire East to reduce the claim for
side trimming to P900,000.00. Capitol’s claim for
foundation excavation was not acted upon. During the construction
period, Empire East granted, on separate occasions, Capitol’s
request for payroll and material accommodations.
On
March 13, 1999, Capitol submitted its final billing amounting to P4,
442,430.90 representing work accomplishment and retention, less all
deductions. Empire East, on the other hand, refused to issue a
certificate of completion. It instead sent a letter to Capitol
informing the latter that it was already in default. Thus,
Capitol was constrained to file a Request for Adjudication.
CIAC found for capitol. On appeal, the Court of Appeals reduced the amount of the award.
The
first issue was whether Capitol was entitled to the release of the 10%
retention money. This is a portion of the contract price deducted from
the contractor’s billings as security for the execution of
corrective works – if any becomes necessary. Among the
contractual pre-conditions for release of this amount to Capitol are:
(a) to submission of the Contractor’s sworn statement showing
that all taxes due from the Contractor, and all obligations on
materials used and labor employed in connection with the contract have
been duly paid; (b) the issuance by the Contractor of a Guarantee Bond
to answer for faulty and/or defective materials or workmanship; and (c)
original and signed and sealed “as built drawings” in three
sets. Both CIAC and the CA held that the non-issuance by Empire East of
the certificate of completion – which was a prerequisite to the
issuance of a Guarantee Bond – this condition was deemed
fulfilled because Empire East voluntarily prevented its fulfillment.
The Supreme Court agreed. But this rule, the Court said, cannot apply
to conditions (a) and (c). Since there was no proof that these
conditions (a) and (c) were complied with, Empire East’s
obligation to release the retention money had not yet arisen. The
Court added that: “We would like to emphasize that this is
without prejudice to Capitol’s compliance with the unfulfilled
conditions, after which, the release of the retention money must,
perforce, follow.”
The
second issue concerned the right of Capitol to overhead costs.
Capitol claimed P13,976,427.00 as additional overhead expenses brought
about by the delay in the completion of the project due to acts
attributable to Empire East. On this point, the Court said: “It
is undisputed that the only piece of evidence presented by respondent
(Capitol) in support of its claim for additional overhead cost was its
own computation of the said expense. It failed to adduce actual
receipts, invoices, contracts and similar documents. To be sure,
respondent’s claim for overhead cost may be classified as a claim
for actual damages. Actual damages are those damages which the
injured party is entitled to recover for the wrong done and injuries
received when none were intended. They indicate such losses as
are actually sustained and are susceptible of measurement.. As
such, they must be proven with a reasonable degree of certainty.
Back to top
This article
was prepared by Custodio O. Parlade, of-counsel of the Parlade Hildawa
Parlade Eco & Panga and president emeritus of the Philippine
Dispute Resolution Center, Inc. For further information on this topic,
please contact Custodio O. Parlade at (632) 687 5362; by mail at 26th
Floor, The Orient Square, F. Ortigas, Jr., Ortigas Center, Pasig City
1605 Philippines, or by e-mail at: coparlade@phpeplaw.com or
gingparlade@yahoo.com.
©
2005 by Philippine Dispute Resolution Center, Inc. (PDRCI)
Please contact
us
for further information.
Steve's
web
templates |